Operator

(Operator Instructions). Our first question will come from the line of Daniele Seitz with Dahlman Rose. Please go ahead.

Benjamin Fowke

Hi Daniele.

Daniele Seitz - Dahlman Rose

Hi. I just wanted to ask you a couple of questions on the CapEx. Can you give us an idea of the estimates on the costs of the wind farm?

Benjamin Fowke

Yea, the wind farm will be approximately 210 million Daniele.

Daniele Seitz - Dahlman Rose

Okay, and could you remind us of the total CapEx for this year and next year?

Benjamin Fowke

It’s about 1.9 billion.

Daniele Seitz - Dahlman Rose

And same thing for both years?

Benjamin Fowke

I’m sorry, what?

Daniele Seitz - Dahlman Rose

Same for both years?

Benjamin Fowke

Yea, I’m sorry that’s about the number for both years.

Daniele Seitz - Dahlman Rose

Ok, great and when do you anticipate, what are you thinking of, in terms of schedule on the IGCC at this time?

Benjamin Fowke

What we are planning to do is present it as an option for the commission to review when we file our least cost plan, our resource plan, in Colorado in the fall of this year Daniele.

Daniele Seitz - Dahlman Rose

Okay, and assuming that it takes a year for the decision to be made, would you start immediately at that point or is there some lead times, approximate dates you are thinking you could build it for?

Benjamin Fowke

I’m sorry Daniele, yeah, there are certainly lead times. The next step in the process, in addition to filing as an option, is to then do the feed study, which will take us into next year. Then we will understand if the project’s approved or not, and we’ll go forward. And if the project were to go forward I think you’re looking at the 2013-2014 timeframe, correct me if I’m wrong.

Daniele Seitz - Dahlman Rose

Thanks, appreciate.

Benjamin Fowke

Thank you.

Operator

Thank you. The next question will come from the line of Paul Ridzon with Key Bank. Please go ahead.

Benjamin Fowke

Hey Paul.

Paul Ridzon - Key Bank

How are you? Congratulations on the quarter. I had a couple of questions. You threw out a $31 million number, potential nuclear depreciation decrease. Is that for ’07 or is that on a four year basis?

Benjamin Fowke

No, that number assumes that the commission approves it and follows the past present of putting it all the way back at the beginning of January 2007.

 

BNET TalkbackShare your ideas and expertise on this topic

Please add your comment:

  1. You are currently: a Guest |
  2.  

Basic HTML tags that work in comments are: bold (<b></b>), italic (<i></i>), underline (<u></u>), and hyperlink (<a href></a)

advertisement
advertisement
  • Click Here
  • Click Here
  • Click Here
advertisement